Explosive Demolition · Regulations

12 August 2027: new rules for demolition with explosives

The amendment of 12 August 2026 to the Regulation on the Demolition of Buildings enters into force one year later. For every demolition with explosives and for the demolition of high-rise buildings, the demolition plan will be prepared in accordance with the new Annex 5.

12.082027Date of entry into force (Art. 14)
21,50mHigh-rise building: building height threshold
135dBAir overpressure upper limit (Annex 5)

01Amendment

What changes?(6)

Official Gazette 12.08.2026/33338. Permit procedures for buildings tendered by public bodies before 12.08.2027 and not yet issued a demolition permit are concluded under the previous provisions (provisional Art. 2).

  • 01

    All demolitions with explosives fall under Annex 5

    The demolition plan for demolitions with explosives and for high-rise buildings is prepared in accordance with Annex 5; all demolitions with explosives are carried out under the provisions on the demolition of high-rise buildings with explosives.

  • 02

    Definition of a high-rise building

    Buildings with a building height above 21.50 m or a structure height above 30.50 m; above 51.50 m and 60.50 m they are very high-rise buildings.

  • 03

    Engineer responsible for blasting

    A civil, mining, environmental, geological or geophysical engineer holding a certificate on the use of explosives issued by institutions authorised by the Ministry, or at least a master’s degree with thesis in demolition with explosives. Is present on site together with the plan author and submits the Form-6 undertaking.

  • 04

    Technical supervisor and blaster

    Technical supervision is mandatory in demolitions with explosives; in addition, an engineer responsible for blasting and a blaster holding a (B) class competency certificate are assigned.

  • 05

    Monitoring and recording

    No blast may be fired without assessing the meteorological conditions. Calibrated vibration and pressure sensors are used at the moment of the blast and the demolition is recorded with high-speed cameras.

  • 06

    Site protection and test blast

    The site perimeter is protected with screening, covered walkways and protective fans. A test blast may be carried out before demolition; if it is, Form-8 is completed.

02Method

How is the demolition method selected?

Annex 5 Figure 1.2 and Art. 2.2.1.

  1. 01

    Zone of influence

    A zone of influence is defined at 2.5 times the building height from the façades; sensitive structures within it are identified and reported.

  2. 02

    Collapse onto its own footprint

    A clear distance of half the building height is required around the building.

  3. 03

    Toppling in a set direction

    An uninterrupted clear distance of at least 1.5 times the height is required; otherwise the design makes the building collapse into itself and then topple in a set direction.

  4. 04

    Impact cushion

    In the toppling method, an impact cushion of sand, soil or similar material is built in the area where the building will fall.

03Limit values

Vibration, air overpressure and weather(6)

The limits of Annex 2 Table 3 of the Environmental Noise Control Regulation also apply; the stricter of the two tables governs.

20–40 mm/s

Commercial, industrial and non-residential buildings

Peak particle velocity (Annex 5 Table 3).

5–15 mm/s

Dwellings

Peak particle velocity (Annex 5 Table 3).

3–8 mm/s

Sensitive structures

Adobe, old or historic buildings (Annex 5 Table 3).

135 dB

Air overpressure

Air overpressure above 135 dB is not permitted.

−5 … 35 °C

Temperature

Permissible range for blasting (Annex 5 Table 4).

1 … 28 km/sa

Wind speed

Permissible range for blasting (Annex 5 Table 4).

04Design

How does Annex 5 describe the demolition design?(6)

We perform collapse analysis with our in-house DTEX CAE software.

  • 01

    Numerical modelling

    The structural system is modelled with discrete or finite element methods and a nonlinear dynamic analysis is performed; each blast step is shown in the report.

  • 02

    Wedge geometry

    In the toppling method one of four wedge types is selected; the centre of gravity, the hinge and the wedge height are calculated.

  • 03

    Charge quantity

    Volume-based method; specific charge between 0.5 and 1.6 kg/m³. Hole length is 2/3 of the member thickness, half of it charged and half stemmed.

  • 04

    Detonators

    Non-electric nonel, delay nonel and electronic detonators and detonating cord are used; electric detonators are not permitted.

  • 05

    Test blast

    If the specific charge is to be used outside the range, a successful test blast is reported on Form-8.

  • 06

    After the blast

    Entry to the site is subject to the permission of the engineer responsible for blasting; no worker enters until respirable dust falls to 5 mg/m³.

05Document set

Forms and report templates(11)

Official forms with the layout of the official text, in Word and PDF. Available to DTEX clients only; sign in to download.

  • F1

    Form-1 Demolition Permit Form

    Annex 1 · issued by the authority · with explanatory pages
    Word · PDF

  • F2

    Form-2 Plan author undertaking

    EK-4
    Word · PDF

  • F3

    Form-3 Technical supervisor undertaking

    EK-4
    Word · PDF

  • F4

    Form-4 Site manager undertaking

    EK-4
    Word · PDF

  • F5

    Form-5 Contractor undertaking

    EK-4
    Word · PDF

  • F6

    Form-6 Undertaking of the engineer responsible for blasting

    EK-4
    Word · PDF

  • F7

    Form-7 Condition Assessment Form

    Annex 6 · clickable check boxes
    Word · PDF

  • F8

    Form-8 Test Blast Evaluation Form

    Annex 6 · clickable check boxes
    Word · PDF

  • R1

    Acoustic report template

    In the order of Annex 3 · DTEX
    Word · PDF

  • R2

    Blasting method and plan report template

    Annex 5 Arts. 1.1.11 and 2.2 · DTEX
    Word · PDF

  • R3

    Test blast report template

    Annex 5 Art. 2.2.5 · DTEX
    Word · PDF

06FAQ

Frequently asked questions

Does Annex 5 apply only to high-rise buildings?

No. Whatever the height, the demolition plan for every demolition with explosives is prepared in accordance with Annex 5.

Does the amendment apply today?

Most of the amendment enters into force on 12 August 2027. The provision that entered into force on publication concerns demolitions carried out by public bodies under Law No. 6306.

Is a test blast mandatory?

The Regulation provides that a test blast may be carried out. If the specific charge is to be used outside 0.5–1.6 kg/m³, a successful test blast must be reported on Form-8.

Who prepares the acoustic report?

Persons holding the competence set out in the Environmental Noise Control Regulation; their training documents are attached to the report.

Contact

Preparing your demolition plan under the 2027 rules?

Tell us the building’s location, height and surroundings; we will support you with the blast design, the acoustic report and the document set.

  • 01Location
  • 02Height and number of storeys
  • 03Distance to neighbouring buildings
  • 04Photographs