Explosive Demolition · Regulations
12 August 2027: new rules for demolition with explosives
The amendment of 12 August 2026 to the Regulation on the Demolition of Buildings enters into force one year later. For every demolition with explosives and for the demolition of high-rise buildings, the demolition plan will be prepared in accordance with the new Annex 5.
01Amendment
What changes?(6)
Official Gazette 12.08.2026/33338. Permit procedures for buildings tendered by public bodies before 12.08.2027 and not yet issued a demolition permit are concluded under the previous provisions (provisional Art. 2).
- 01
All demolitions with explosives fall under Annex 5
The demolition plan for demolitions with explosives and for high-rise buildings is prepared in accordance with Annex 5; all demolitions with explosives are carried out under the provisions on the demolition of high-rise buildings with explosives.
- 02
Definition of a high-rise building
Buildings with a building height above 21.50 m or a structure height above 30.50 m; above 51.50 m and 60.50 m they are very high-rise buildings.
- 03
Engineer responsible for blasting
A civil, mining, environmental, geological or geophysical engineer holding a certificate on the use of explosives issued by institutions authorised by the Ministry, or at least a master’s degree with thesis in demolition with explosives. Is present on site together with the plan author and submits the Form-6 undertaking.
- 04
Technical supervisor and blaster
Technical supervision is mandatory in demolitions with explosives; in addition, an engineer responsible for blasting and a blaster holding a (B) class competency certificate are assigned.
- 05
Monitoring and recording
No blast may be fired without assessing the meteorological conditions. Calibrated vibration and pressure sensors are used at the moment of the blast and the demolition is recorded with high-speed cameras.
- 06
Site protection and test blast
The site perimeter is protected with screening, covered walkways and protective fans. A test blast may be carried out before demolition; if it is, Form-8 is completed.
02Method
How is the demolition method selected?
Annex 5 Figure 1.2 and Art. 2.2.1.
- 01
Zone of influence
A zone of influence is defined at 2.5 times the building height from the façades; sensitive structures within it are identified and reported.
- 02
Collapse onto its own footprint
A clear distance of half the building height is required around the building.
- 03
Toppling in a set direction
An uninterrupted clear distance of at least 1.5 times the height is required; otherwise the design makes the building collapse into itself and then topple in a set direction.
- 04
Impact cushion
In the toppling method, an impact cushion of sand, soil or similar material is built in the area where the building will fall.
03Limit values
Vibration, air overpressure and weather(6)
The limits of Annex 2 Table 3 of the Environmental Noise Control Regulation also apply; the stricter of the two tables governs.
20–40 mm/s
Commercial, industrial and non-residential buildings
Peak particle velocity (Annex 5 Table 3).
5–15 mm/s
Dwellings
Peak particle velocity (Annex 5 Table 3).
3–8 mm/s
Sensitive structures
Adobe, old or historic buildings (Annex 5 Table 3).
135 dB
Air overpressure
Air overpressure above 135 dB is not permitted.
−5 … 35 °C
Temperature
Permissible range for blasting (Annex 5 Table 4).
1 … 28 km/sa
Wind speed
Permissible range for blasting (Annex 5 Table 4).
04Design
How does Annex 5 describe the demolition design?(6)
We perform collapse analysis with our in-house DTEX CAE software.
- 01
Numerical modelling
The structural system is modelled with discrete or finite element methods and a nonlinear dynamic analysis is performed; each blast step is shown in the report.
- 02
Wedge geometry
In the toppling method one of four wedge types is selected; the centre of gravity, the hinge and the wedge height are calculated.
- 03
Charge quantity
Volume-based method; specific charge between 0.5 and 1.6 kg/m³. Hole length is 2/3 of the member thickness, half of it charged and half stemmed.
- 04
Detonators
Non-electric nonel, delay nonel and electronic detonators and detonating cord are used; electric detonators are not permitted.
- 05
Test blast
If the specific charge is to be used outside the range, a successful test blast is reported on Form-8.
- 06
After the blast
Entry to the site is subject to the permission of the engineer responsible for blasting; no worker enters until respirable dust falls to 5 mg/m³.
05Document set
Forms and report templates(11)
Official forms with the layout of the official text, in Word and PDF. Available to DTEX clients only; sign in to download.
- F1
- F2
- F3
- F4
- F5
- F6
- F7
- F8
- R1
- R2
- R3
06FAQ
Frequently asked questions
Does Annex 5 apply only to high-rise buildings?
No. Whatever the height, the demolition plan for every demolition with explosives is prepared in accordance with Annex 5.
Does the amendment apply today?
Most of the amendment enters into force on 12 August 2027. The provision that entered into force on publication concerns demolitions carried out by public bodies under Law No. 6306.
Is a test blast mandatory?
The Regulation provides that a test blast may be carried out. If the specific charge is to be used outside 0.5–1.6 kg/m³, a successful test blast must be reported on Form-8.
Who prepares the acoustic report?
Persons holding the competence set out in the Environmental Noise Control Regulation; their training documents are attached to the report.
Contact
Preparing your demolition plan under the 2027 rules?
Tell us the building’s location, height and surroundings; we will support you with the blast design, the acoustic report and the document set.
- 01Location
- 02Height and number of storeys
- 03Distance to neighbouring buildings
- 04Photographs
—Related pages